Summary: The county data has 3,277 permits for home additions in the ZIP codes 20814, 20815, 20816 and 20817. These ZIP codes include Bethesda and Chevy Chase. The county gave the permits from 2015 to 2025. The work description of 852 permits shows a second story. These permits are 26 percent of the addition permits.
The median second-story addition has an area of 1,068 square feet (SF) and a declared cost of USD 200,000. The median is the middle value. A rear addition has a median area of 460 SF and a median declared cost of USD 100,000.
The median time from the application to the permit is 41 days for a second-story addition. For a rear addition, the median is 34 days. After the permit, the median time to the final inspection is 301 days for a second-story addition and 241 days for a rear addition. The last two numbers are only for the permits from 2015 to 2022 that have a date of the final inspection.

How we read the data
Montgomery County shows the data of its residential permits on its open data website. Each row of the data is one permit. The row has the date of the application and the date of the permit. The row also has the work type, the work description, the area and the declared cost. For some permits, the row has the date of the final inspection.
We selected the permits that have the work type "ADD" (addition) and the code "SINGLE FAMILY DWELLING". We selected the permits that the county gave from 2015 to 2025. We used full years only. The data has 3,277 of these permits. We also read 4,654 "ALTER" permits. We used them only to find the words for a second story.
We put each addition permit in one of three groups. We used the words of the work description:
- Second-story: the work description has words, for example "second floor", "second story", "second level", "2nd story" or "two-story".
- Rear: the work description has the word "rear" and has no word for a second story.
- Other: all the other addition permits. A permit with no work description is in this group.
3,254 of the 3,277 permits have a work description. The share is 99.3 percent. The groups have 852 second-story permits, 377 rear permits and 2,048 other permits.
The applicant gives the area and the declared cost to the county. The area is the area of the work. It is not the area of the home. The declared cost is the cost that the applicant gives. It is not the cost in a contract.
For the tables on the area and the cost, we used only some permits. These permits have an area of 100 SF or more. They also have a declared cost of USD 20,000 or more.
The time to the permit is the number of days from the date of the application to the date of the permit. The time to the final inspection is the number of days from the date of the permit to the date of the final inspection. Only a permit with a date of the final inspection has this time. For this time, we used only the permits that the county gave from 2015 to 2022. The work in a permit of the subsequent years can be in progress.
Second-story permits for each year
The table that follows gives the number of permits for each year of the permit.
| Year of the permit | Addition permits | Second-story permits | Share of the addition permits | Rear permits |
|---|---|---|---|---|
| 2015 | 347 | 85 | 24 percent | 30 |
| 2016 | 340 | 77 | 23 percent | 33 |
| 2017 | 324 | 67 | 21 percent | 20 |
| 2018 | 276 | 55 | 20 percent | 9 |
| 2019 | 302 | 55 | 18 percent | 13 |
| 2020 | 276 | 67 | 24 percent | 32 |
| 2021 | 337 | 95 | 28 percent | 65 |
| 2022 | 306 | 104 | 34 percent | 48 |
| 2023 | 290 | 96 | 33 percent | 45 |
| 2024 | 241 | 77 | 32 percent | 39 |
| 2025 | 238 | 74 | 31 percent | 43 |
The number of second-story permits for each year is from 55 to 104. The average is 77 permits for each year. The share of the addition permits is also different for each year. The data does not show the cause.
The rear permits are 11.5 percent of the addition permits. A rear addition with no word "rear" in the work description is in the group "other". Thus, the number of rear additions can be more than the number of permits in the group "rear".
The area and the declared cost
The table that follows gives the median values of the permits with an area and a cost.
| Group | Permits with an area and a cost | Median area | Median declared cost | Median declared cost for each SF |
|---|---|---|---|---|
| Second-story | 822 | 1,068 SF | USD 200,000 | USD 177 |
| Rear | 335 | 460 SF | USD 100,000 | USD 206 |
| Other | 1,564 | 403 SF | USD 97,000 | USD 188 |
| All additions | 2,721 | 574 SF | USD 120,000 | USD 187 |

The median area of a second-story addition is 608 SF larger than the median area of a rear addition. It is 2.32 times the median area of a rear addition. The median declared cost is USD 100,000 higher. It is 2.0 times the median declared cost of a rear addition.
The median declared cost for each SF is lower for a second-story addition than for a rear addition. It is 0.86 times the median of a rear addition. The data does not show the cause.
The table that follows gives the values for 25, 50, 75 and 90 percent of the 822 second-story permits with an area and a cost.
| Permits | Area | Declared cost |
|---|---|---|
| 25 percent of the permits | not more than 600 SF | not more than USD 101,000 |
| 50 percent of the permits (the median) | not more than 1,068 SF | not more than USD 200,000 |
| 75 percent of the permits | not more than 1,799 SF | not more than USD 300,000 |
| 90 percent of the permits | not more than 2,817 SF | not more than USD 500,000 |
The permits are from many years. The cost of work changes each year. The numbers on this page do not change the declared costs for these changes. Thus, a declared cost of one year and a declared cost of a different year are not for the same cost of work.
The time from the application to the permit
The time to the permit is for all 852 second-story permits, 377 rear permits and 2,048 other permits. The table that follows gives the longest time for 25, 50, 75 and 90 percent of the permits of each group.
| Group | 25 percent of the permits | 50 percent (the median) | 75 percent of the permits | 90 percent of the permits |
|---|---|---|---|---|
| Second-story | 24 days | 41 days | 67 days | 119 days |
| Rear | 18 days | 34 days | 59 days | 89 days |
| Other | 10 days | 24 days | 44 days | 79 days |
| All additions | 14 days | 29 days | 52 days | 93 days |
The median time for a second-story addition is 7 days longer than the median time for a rear addition. It is 1.21 times the median time for a rear addition. For 10 percent of the second-story permits, the time is 119 days or more.
The time can include days when the applicant corrects the plans. The data does not show the cause of a long time.
The time from the permit to the final inspection
For this part, we used the permits that the county gave from 2015 to 2022. The table that follows gives the number of permits that have a date of the final inspection.
| Group | Permits from 2015 to 2022 | Permits with a final inspection | Share of the permits |
|---|---|---|---|
| Second-story | 605 | 498 | 82 percent |
| Rear | 250 | 201 | 80 percent |
| Other | 1,653 | 1,367 | 83 percent |
The table that follows gives the longest time for 25, 50, 75 and 90 percent of the permits with a final inspection.
| Group | 25 percent of the permits | 50 percent (the median) | 75 percent of the permits | 90 percent of the permits |
|---|---|---|---|---|
| Second-story | 214 days | 301 days | 411 days | 567 days |
| Rear | 162 days | 241 days | 388 days | 595 days |
| Other | 121 days | 215 days | 350 days | 530 days |

The median time for a second-story addition is 60 days longer than the median time for a rear addition. It is 1.25 times the median time for a rear addition. The median for a second-story addition is approximately 10 months. The median for a rear addition is approximately 8 months.
These times are only for permits with a date of the final inspection. The permits with no date of the final inspection are not in them. For some of these permits, the work can be in progress. Thus, the median time for all permits can be longer. The time can also include days with no work.
Second-story additions of different areas
We put the permits with an area and a cost in three groups of area: less than 500 SF, 500 to 999 SF, and 1,000 SF or more. The table that follows gives the second-story permits in these groups.
| Area of the work | Second-story permits | Share of the permits with an area and a cost | 25 percent of the permits | Median declared cost | 75 percent of the permits |
|---|---|---|---|---|---|
| Less than 500 SF | 152 | 18 percent | not more than USD 75,000 | USD 120,000 | not more than USD 214,000 |
| 500 to 999 SF | 237 | 29 percent | not more than USD 95,000 | USD 150,000 | not more than USD 250,000 |
| 1,000 SF or more | 433 | 53 percent | not more than USD 150,000 | USD 250,000 | not more than USD 400,000 |
53 percent of the 822 second-story permits with an area and a cost are in the group of 1,000 SF or more. For the rear permits with an area and a cost, the share of this group is 25 percent. For the other permits with an area and a cost, the share is 22 percent. The share of each group of area is different in the three groups. Thus, the table that follows compares the median declared cost of the three groups for each area.
| Area of the work | Second-story: median declared cost | Rear: median declared cost | Other: median declared cost |
|---|---|---|---|
| Less than 500 SF | USD 120,000 | USD 80,000 | USD 60,000 |
| 500 to 999 SF | USD 150,000 | USD 125,000 | USD 127,000 |
| 1,000 SF or more | USD 250,000 | USD 250,000 | USD 275,000 |
Information that these numbers do not give
The numbers do not give this information:
- The cost of a project. The declared cost is the cost that the applicant gives. It is not a cost in a contract. The cost in a contract can be higher or lower.
- The number of projects. A project can have more than one permit. The number of permits is not the number of projects.
- Each second-story addition. We made the groups from words in the work description. A second-story addition with none of these words is not in the group "second-story". It can be in the group "other".
- The "ALTER" permits. Some second-story work has the work type "ALTER". 221 of the 4,654 "ALTER" permits have words for a second story. These permits are not in the groups of this page.
- The time for a permit with no final inspection. The time to the final inspection is only for permits that have a date of the final inspection. The permits are from 2015 to 2022.
- The time before the application.
- The change of the cost of work each year. The cost of work changes each year.
- The cause of a difference in cost or time between the groups.
Information for an owner of a large project
In the data, the median area of a second-story addition is larger than the median area of a rear addition. The median declared cost is also higher. The two median times are also longer.
For a second-story addition, the median time to the permit is 41 days. For 10 percent of the permits, the time is 119 days or more. After the permit, the median time to the final inspection is 301 days. For 10 percent of the permits with a final inspection, the time is 567 days or more. The share of the permits with a final inspection is 82 percent. Thus, the times for all permits can be longer.
A median does not show the time or the cost of your project. The time and the cost of your project can be different. The declared cost in the data is not the cost of your project. You can tell your contractor to give you a cost in a contract and a plan with dates for the work. You can also tell your contractor to give the date of each inspection.
Questions and answers
The number of second-story addition permits in Bethesda and Chevy Chase
The data has 852 second-story permits from 2015 to 2025 in the ZIP codes 20814 to 20817. The number for each year is from 55 to 104. The number of permits is not the number of projects.
The median area and declared cost of a second-story addition
The median area is 1,068 SF. The median declared cost is USD 200,000. For rear additions, the median area is 460 SF and the median declared cost is USD 100,000. The declared cost is not the cost in a contract.
Is the time to the permit longer for a second-story addition than for a rear addition?
Yes, in the data. The median time from the application to the permit is 41 days for a second-story addition and 34 days for a rear addition. The data does not show the cause.
Is the time to the final inspection longer for a second-story addition?
Yes, in the data. The median time from the permit to the final inspection is 301 days for a second-story addition and 241 days for a rear addition. These medians are only for permits with a date of the final inspection. The permits are from 2015 to 2022.
Is the declared cost the cost in a contract?
No. The declared cost is the cost that the applicant gives to the county. The cost in a contract can be higher or lower.
Do you want a second-story addition in Bethesda or Chevy Chase?
We can help you to schedule the work of your project. Request a Consultation.
You can also read: The Time for an Addition Permit in Bethesda and Chevy Chase
You can also read: The Declared Cost of a Home Addition in Bethesda and Chevy Chase
You can also read: The Time From the Permit to the Final Inspection for an Addition in Bethesda and Chevy Chase
Sources
- The source of the data is the dataset "Residential Permit" of the open data of Montgomery County (data.montgomerycountymd.gov).
- The data is for the permits with the work type "ADD" (addition) and for single-family homes in the ZIP codes 20814 to 20817. The county gave the permits from 2015 to 2025. The "ALTER" permits are only for the words for a second story.
- We made the groups "second-story", "rear" and "other" from the work description of the permit.
- The time to the final inspection is for the permits that the county gave from 2015 to 2022.
- We used a script to calculate the numbers from the county data.